A Facility Security Level (FSL) is the category, from Level I (lowest risk) to Level V (highest risk), that the Interagency Security Committee's Risk Management Process assigns to a nonmilitary federal facility. In the standard it has two jobs: it points planners to a baseline set of countermeasures for new construction or a new lease, and it sets how often the facility's risk is reassessed. 1
The FSL matrix scores five equally weighted factors at 1 to 4 points each: mission criticality, symbolism, facility population, facility size and threat to tenant agencies. Population bands run from fewer than 100 people to more than 750, and a facility with a child-care center receives the top population value. Size bands run from under 10,000 to over 250,000 square feet. In a building with several federal tenants, the highest rating of any tenant is used for mission criticality and for threat. The sum gives a preliminary level: 5 to 7 points is Level I, 8 to 12 Level II, 13 to 17 Level III and 18 to 20 Level IV. 1
A sixth element, intangibles, lets the security organization and responsible authority raise or lower the level by one, with the reasons documented. The standard says intangibles are not to be used to raise the FSL in response to a particular threat, which is the job of the risk assessment, and not to reduce the baseline protection. Level V is not reached by points. Its criteria and the decision rest with each agency, and the standard suggests a facility may suit Level V if it scores high for mission criticality or symbolism and is one of a kind or nearly so. 1
Each FSL corresponds to a baseline Level of Protection, from Minimum for Level I to Very High for Level V; the countermeasures for each level are in the restricted Appendix B. Once a risk assessment is complete the necessary Level of Protection replaces the baseline, but the FSL still applies, including for the reassessment interval: every five years for Levels I and II and every three years for Levels III, IV and V. 1
The tenants make the final determination in consultation with the owning or leasing authority and the security organization; in a multi-tenant facility they do so through the Facility Security Committee. If the parties disagree, an ISC regional advisor may facilitate, and unresolved cases go to the agencies' senior officials. The final FSL is documented, signed and retained. 1 The 2024 edition's list of changes says it updated the matrix values to match other values in the process. 1
Source · The Risk Management Process: An Interagency Security Committee Standard, 2024 Edition (Version 4.0) (opens in a new tab) · Interagency Security Committee, CISA